We have passed all rough-in inspections and the spray insulation is going in today. Because of the harmful fumes nobody else can work at the site today. But things will really pick up tomorrow. Batt insulation, interior door installation and painting all should happen this week. The gypsum board is scheduled for next week and finishes will follow beginning of Septemeber.
We have passed electrical inspection and are just days away of having all the rough-in inspections done. Fire places are in. It's a true race with time...